Critical Path Analyzer
Identify the critical path for project scheduling and optimization
Project Duration
Minimum time to complete project
40 days
Critical Path
Tasks that cannot be delayed
A → B → C → D → E
Project Tasks
Enter task details and dependencies
Detailed Schedule
ES = Earliest Start, EF = Earliest Finish, LS = Latest Start, LF = Latest Finish, Slack = Float Time
| Task | Duration | ES | EF | LS | LF | Slack | Critical? |
|---|---|---|---|---|---|---|---|
A: Project Planning | 5 | 0 | 5 | 0 | 5 | 0 | Critical |
B: Design After: A | 10 | 5 | 15 | 5 | 15 | 0 | Critical |
C: Development After: B | 15 | 15 | 30 | 15 | 30 | 0 | Critical |
D: Testing After: C | 7 | 30 | 37 | 30 | 37 | 0 | Critical |
E: Deployment After: D | 3 | 37 | 40 | 37 | 40 | 0 | Critical |