Critical Path Analyzer

Identify the critical path for project scheduling and optimization

Project Duration
Minimum time to complete project
40 days
Critical Path
Tasks that cannot be delayed
A → B → C → D → E
Project Tasks
Enter task details and dependencies
Detailed Schedule
ES = Earliest Start, EF = Earliest Finish, LS = Latest Start, LF = Latest Finish, Slack = Float Time
TaskDurationESEFLSLFSlackCritical?
A: Project Planning
505050Critical
B: Design
After: A
105155150Critical
C: Development
After: B
15153015300Critical
D: Testing
After: C
7303730370Critical
E: Deployment
After: D
3374037400Critical