Task Dependency Visualizer
Visualize task dependencies and calculate critical path for project planning
Project Summary
5
Total Tasks
45
Days Duration
45
Total Effort Days
Add New Task
Define task details and dependencies
Task Timeline
Requirements Gathering
Day 0-5
5d
Design
Day 5-15
10d
Depends on: Requirements Gathering
Development
Day 15-35
20d
Depends on: Design
Testing
Day 35-42
7d
Depends on: Development
Deployment
Day 42-45
3d
Depends on: Testing
Task Details & Dependencies
| Task | Duration | Start | End | Dependencies |
|---|---|---|---|---|
| Requirements Gathering | 5 days | Day 0 | Day 5 | None |
| Design | 10 days | Day 5 | Day 15 | Requirements Gathering |
| Development | 20 days | Day 15 | Day 35 | Design |
| Testing | 7 days | Day 35 | Day 42 | Development |
| Deployment | 3 days | Day 42 | Day 45 | Testing |